Saudi Arabia: Arabian Cement says that the Jeddah Commercial Court has ruled in its favour in a lawsuit it filed against Emaar, the Economic City Company, to claim outstanding quantities of limestone it was due in an agreement the companies signed in 2012. The court has ordered Emaar to give Arabian Cement around 4.6Mt of limestone. As part of the deal, from 2012 to 2018, Emaar agreed to provide the cement company with 44.7Mt of limestone. However, Arabian Cement maintains that it did not receive 5.3Mt of the total.
Arabian Cement previously gave land to Emaar in return for a limestone supply deal. Emmar company has been developing the King Abdullah Economic City.