Golden Bay Cement hit by four-week stoppage in September 2018

Print this page

New Zealand: Fletcher Building says that its Golden Bay Cement plant in Auckland was forced stop its cement mill for four weeks in September 2018. It said it had insurance to cover this but that its earnings for its 2019 financial year are likely to be impacted by up to US$8m. Generally, the building materials producer reported that, until the end of October 2018, its business in New Zealand had been flat. In Australia it is facing ‘challenging’ conditions with growing input prices and a slowing residential sector.

Last modified on 21 November 2018

Register for the Global Cement Weekly email newsletter

Global Cement Weekly is Global Cement’s weekly email newsletter. Keep up to date with cement industry news, analysis, diary dates and news of people in the sector.

Register >

URL: https://www.globalcement.com/news/item/8349-golden-bay-cement-hit-by-four-week-stoppage-in-september-2018

© 2024 Pro Global Media Ltd. All rights reserved.