Saudi Arabia: ABB has commissioned an electrical infrastructure upgrade for the Eastern Province Cement Company’s (EPCC) two cement production lines at its plant in Al Khursaniya. The project upgraded the existing 75MV Switchgear Panels and integrated the power supply systems with the ABB 800xA automation system already in place. Commissioning was completed in February 2016.
“ABB has completed the final upgrade on site in a record time during the planned maintenance shutdowns of the plant,” said Mohammad Arif Khan, Electrical and Instrumentation Manager at EPCC. “The excellent teamwork between EPCC and ABB engineers made it possible to meet this challenge without affecting the production of the other production lines.”
The scope of supply included the replacement of the 30-year old protection compartment of 75MV (13.8kV and 4.16kV) Switchgear Panels with the latest generation of ABB Relion protection relays, integration via IEC61850 with the 800xA automation system and the delivery of computer and network equipment. ABB also provided project management, engineering, site services and training together with its supplier EcoWatt Projects.