US: FCT Combustion has reported service updates to its clients in Ecuador, the US and Canada.
Hormicreto in Cuenca, Ecuador is preparing for commissioning of its G-Jet Hot Gas Generator for alternative liquid fuels firing, with a thermal capacity of 5.2MW. The system will provide hot air for the raw and cement swing mill application. FCT is responsible for the complete supply from the waste oil tank to the hot gas generator. Hormicreto is also commissioning a new riser duct natural gas firing system. FCT has also supplied two K-Jet Calciner Burners at the riser.
The Lehigh Cement Leeds plant in Alabama, US has awarded FCT with a new contract for a natural gas firing system for their riser duct. The system, rated at 30MW, will consist of a NPFA 86 Valve Train and K-JetCalciner Burner.
St Marys Cement, part of the Votorantim Group, has ordered, via Arctic Combustion, two K-Jet Calciner Burners for natural gas at the riser for its Ontario, Canada plant. The K-Jet Burner has a cutter block system that adjusts gas velocity on the fly during operation.
The CRH Mississauga plant in Canada has hired FCT to make an audit of several of its pieces of combustion equipment of the plant.