Udayapur Cement production hampered by power cuts

Print this page

Nepal: Udayapur Cement’s production is being reduced due to power cuts. The plant has a production capacity of 800t/day of clinker but at times it has been reduced to only just 100t/day, according to the Republica newspaper. The cement producer says that the cuts have cost it over US$0.4m.

The electricity outages have also damaged machinery such as gears in cement-packaging equipment and raised general costs through repeated start-ups. The unit suffered 62 power cuts from 15 January to 2 February 2019 lasting a total of 23 hours. As many as six stoppages in a single day have been reported.

The Nepal Electricity Authority supplies electricity to the plant. It has blamed the ‘incompetence’ of officials at a substation.

Last modified on 12 February 2019

Register for the Global Cement Weekly email newsletter

Global Cement Weekly is Global Cement’s weekly email newsletter. Keep up to date with cement industry news, analysis, diary dates and news of people in the sector.

Register >

URL: https://www.globalcement.com/news/item/8762-udayapur-cement-production-hampered-by-power-cuts

© 2024 Pro Global Media Ltd. All rights reserved.