First phase of Euro28m upgrade to Hanson Cement’s Padeswood plant completed

Print this page

UK: Hanson Cement says that the first phase of a Euro27m upgrade project to its integrated Padeswood plant in Wales has been completed. The upgrade has included the installation of a 0.65Mt/yr cement grinding mill as well as enhancements to production capacity and efficiency gains. The plant can now, with the aid of existing ball mills, match cement grinding with its kiln capacity.

“The nearly new Loesche vertical roller mill, housed in a 34m-high building, started its life at a grinding plant in Bilbao. It had only 7000 operational hours on the clock and was in excellent condition. After dismantling it piece by piece, specialist contractors moved it to the UK where it was reassembled on site at Padeswood,” said Jim Claydon, Hanson UK cement managing director.

Other improvements at the site include the installation of three new rail cement silos that have been installed alongside the existing railhead. This will allow up to three trains a week to be loaded for deliveries to Hanson depots in London, Bristol or Glasgow. The new silos will reduce the transportation of cement produced at Padeswood to customers by road. In addition to the increase in grinding capacity, other recent capital investment at Padeswood include the installation of a plastic packing machine, and the re-commissioning of an existing paper packaging machine and an upgrade in the capability to use recycled paper and plastics as fuel.

Last modified on 10 July 2019

Register for the Global Cement Weekly email newsletter

Global Cement Weekly is Global Cement’s weekly email newsletter. Keep up to date with cement industry news, analysis, diary dates and news of people in the sector.

Register >

URL: https://www.globalcement.com/news/item/9512-first-phase-of-euro28m-upgrade-to-hanson-cement-s-padeswood-plant-completed

© 2024 Pro Global Media Ltd. All rights reserved.