Nepal: Hetauda Cement Industry resumed cement production on 7 April 2025 following a five-month suspension due to electricity shortages. According to general manager Nabin Kumar Karna, the plant requires 8MW/day of electricity to crush limestone.

The plant reportedly holds 1900t of coal in reserve and is acquiring a further 4000t through a bidding process. Though its capacity is 18,000 bags/day, current output is only 12,000 bags/day.

Last modified on 09 April 2025