Austria: Rohrdorfer Group has awarded an engineering, procurement and construction (EPC) contract to Humboldt Wedag, a subsidiary of KHD, for the modernisation of the kiln line at its cement plant operations in Gmunden. The upgrade will enable the flexible usage of a wide range of waste fractionally pre-treated derived fuels on a high substitution rate.
The modernisation project comprises the design and supply of KHD’s world´s first ever Pyrorotor Calciner Technology, as well as the replacement of the existing satellite cooler with a new generation Pyrofloor PFC2 clinker cooler. The existing three station rotary kiln will be fitted with a new kiln drive and a new kiln hood as well as kiln inlet and outlet.
With the installation of the new Pyrorotor Calciner Technology from KHD the Gmunden plant will be able to burn very coarse waste derived fuels including whole rubber tires, which will lead to drastically reduced requirements in regard to waste pre-treatment. Therefore, the kiln modification will also emphasise on pollutant emission reduction.
The contract includes: three new preheater cyclones; a new preheater ID-fan; a tertiary air duct; a Pyrotop compact calciner mixing chamber; Pyrorotor Calciner burning chamber technology, a Pyroclon Calciner Burning System; a new kiln bypass unit; a multi-fuel Pyro-Jet kiln burner for primary and secondary fuels; a new kiln drive and kiln hood; a Pyrofloor PFC2 clinker cooler equipped with a Pyrocrusher roller type clinker crusher; and Simulex plant simulation software.
KHD services include the dismantling of existing equipment parts as well as the engineering, design, supply and erection of new equipment including commissioning services. Commissioning of the new system is scheduled for April 2019.