Russia: Vostokcement subsidiary Teploozorsky Cement has engaged FLSmidth to complete two hot kiln alignments at its integrated Teploozorsky Cement plant in Oblu, Khabarovsk Krai following inspections. Vostokcement said that the plant’s second and third rotary kilns will need to undergo the process of adjustments to their axis and axial balance, in order to eliminate stresses to the kiln body.
Vostokcement installs new belt in Spasskcement plant
28 November 2019Russia: Vostokcement subsidiary Spasskcement received a ninth belt to serve as a back-up for conveying materials into one of its two kilns at its Spasskcement plant. The belt is 7.65m wide and was manufactured in Louyang, China.
Russia: Vostokcement Group has warned both federal and regional government that its on-going legal troubles will delay infrastructure projects in the Far East district, including the Zvezda shipyard, Vostochny Port coal terminal, Sila Sibiri gas pipe and a bridge over the River Amur. It said it also might be unable to pay up to 5000 workers. The cement producer previously said that office of the Prosecutor General of Russia had seized the financial accounts at Spasskcement, Teploozersk Cement and other subsidiaries in relation to a civil legal case where the defendants are trying to recover Euro44.5m.
Wikov Gear sends 120t gearbox to Spassk-Cement in Russia
05 November 2014Russia: Engineering company Wikov Gear will transport a 120t gearbox to a cement plant near Vladivostok, Russia, via road and ship by February 2015. It is the heaviest gearbox Wikov Gear has produced in over 100 years of existence, according to CEO Tomas Zrostlik. Lorries with the gearbox will leave Plzen, western Bohemia, in the middle of November 2014.
The biggest gearbox made by Wikov Gear thus far weighed 102t. It was made for Siemens, which was building a cement roller mill in South Korea. "Before that, we were producing special gearboxes which weighed 60 – 70t, in particular for roller mills' heavy operations," Zrostlik said. Some 80% of the company's portfolio is equipment weighing 20 – 25t.
The gearbox that is destined for Russia is 8m long, 5m high and 2.5m wide. It has been designed for 15 years of operation. The recipient is Spassk-Cement, of the private group Vostok Cement, which has three cement plants and supplies 95% of its output to Russia.
"We will load the equipment within three weeks. It will travel to Hamburg and then by ship via Shanghai. We expect it to arrive in 45 - 50 days," Zrostlik said. The gearbox will be in 25 boxes, the heaviest one weighing 45t. The assembly will start in March 2015 and the launch of its operation is planned for around 15 April 2015. Wikov Gear is also responsible for the assembly and online implemtnation.
Supplies for cement plants have made up 15% of Wikov Gear's turnover thus far, but the share is to rise up to 25% in 2015. The company also won an order from Lafarge in Germany in November 2014.