First clinker manufactured following upgrade at Secil’s Outão plant

Print this page

Portugal: The first batch of clinker has been manufactured on the new upgraded production line at Secil’s Outão plant. Construction and start-up teams from ThyssenKrupp Polysius reached the milestone in mid-April 2023 after a heating period of 72 hours. Germany-based ThyssenKrupp Industrial Solutions was appointed by Secil to work on the Clean Cement Line project in 2020. It said it was going to modify the existing rotary kiln and preheater tower, install a new calciner and add a new grate cooler. Once finished it will produce Portland limestone cement (PLC). It is scheduled for commissioning in mid-2023.

Italy-based CTP Team was contracted in mid-2020 to supply and install a 29MW waste heat recovery (WHR) unit for the project. It planned to use an organic rankine cycle (ORC) unit using a 7.2MW turbine supplied by Turboden.

Italy-based Bedeschi also revealed in early April 2023 that it was in the cold commissioning phase for a new pipe conveyor at the plant to handle different kinds of alternative fuels. The conveyor has a diameter of 250mm and conveying length of 350m and will transport alternative fuels at a rate of 300m3/hr.

Last modified on 21 April 2023

Register for the Global Cement Weekly email newsletter

Global Cement Weekly is Global Cement’s weekly email newsletter. Keep up to date with cement industry news, analysis, diary dates and news of people in the sector.

Register >

URL: https://www.globalcement.com/news/item/15625-first-clinker-manufactured-following-upgrade-at-secil-s-outao-plant

© 2024 Pro Global Media Ltd. All rights reserved.