Malaysia: Borneo Cement Sabah (BCS) is set to commence land works and forest clearance in Tongod district starting early September 2024, following the approval of its site preparation plan by the Sabah Department of Environment on 19 July 2024.
The Borneo Post reports that the cement plant will be fully automated and digitally controlled, with a conveyor used for the 3km stretch between the clinker quarry and the cement processing plant. The project will cost US$274m and will see a new road network spanning 26km from Kampung Matiku, Nabawan to the plant site at Kampung Kayawoi, with additional facilities like a dam and water treatment plant being developed and other facilities for use by local residents.
The first phase of the contract is expected to last a year, with factory operations anticipated to begin as early as January 2026.