Fives becomes founding member of the Centre for Technologies, Minerals and Recycled Materials of the Future
12 September 2017France: Fives Group has revealed its membership of the Centre for Technologies, Minerals and Recycled Materials of the Future, a new association that aims to develop industrial recycling of minerals for the construction and public works sectors. Fives’ Innovation Department and its subsidiary Fives FCB joined Team2 to found the associate in May 2017.
The centre plans to set up a base to coordinate and test by-product valorisation, as well as the use of raw materials recovered from recycling, at a former cement plant owned by EQIOM group in Dannes, Pas-de-Calais. Fives contribution to the research will include its technologies in crushing, grinding, classifying and pyro processing in the minerals industry.
India: France’s Fives has receive an order from AMCL Machinery to supply a new FCB TSV Classifier 4500 THF. The classifier will be used by Ramco Cements at its R R Nagar Plant in Tamil Nadu. Previously the cement producer has installed FCB TSV classifiers at its grinding plants in Kolagat, Salem and Chengalpattu.
Poland: Belgium’s Lhoist has ordered a FCB TSV Classifier 1400 HF from Fives to increase the production of a limestone grinding plant. The unit already operates two FCB TSV Classifiers following upgrades in 1999 and 2016. The classifier will close a circuit, which consisted in a ball mill in open circuit. The installation of this equipment is intended to increase both the grinding line capacity and the finished products quality.
Fives wins dryer contract with Cementos del Norte
13 June 2017Honduras: France’s Fives has won a contract to supply a FCB Flash dryer for Cementos del Norte’s Bijao plant. The dryer will be installed on an existing ball mill that was supplied and installed by Fives FCB in 2001 for a production capacity of 90t/hr of pozzolanic cement. Since then the pozzolana content and moisture rate have increased. Once operational the grinding plant drying capacity will rise.
Algeria: Fives installed the first FCB B cement grinding mill in early April 2017 at Entreprise des Ciments et Dérivés d’El Chellif’s (ECDE) 6000t/day clinker production line at Chlef. Installation of the mill followed the erection of the FCB kiln (Ø 5.1 x L 82m) in February 2017. A heavy lifting jack crane system sliding on rails was required to install the 4.8 x 17.8m shell and 98.5t gearbox inside its specific finished building. Grinding mills no. 2 and no. 3 will be installed next to complete the cement grinding mills at the unit. Once complete it will include three 160t/hr FCB B-mills with 5320kW drives and associated FCB TSV4500 HF classifiers. ECDE is a member of the industrial group Ciments d’Algérie (GICA).
Qatar: France’s Fives has released further information about its work on the 5000t/day cement production line for Qatar National Cement Company. Fives installed the 6.6MW FCB B-mill of the raw meal grinding plant in March 2017. Installation of the raw mill shell was completed on 29 March 2017. The shell weighs 198t, has a length of 17.2m and a diameter of 6.4m. It was moved and erected using a self-propelled modular transporter. This project step followed the commissioning of the two FCB B-mills at the cement grinding plant in January and February 2017, and the signature of the related provisional acceptance in April 2017.
Mexico: Fives has supplied a Fives FCB Horomill for the new production line at Cementos Moctezuma’s Apazapan plant in Veracruz. The cement producer signed the acceptance certificate in mid-February 2017. The FCB Horomill 3800, supplied to fit the raw meal-grinding workshop, is part of the new plant that was inaugurated by Cementos Moctezuma in January 2017.
Fives commissions mills at projects in Mexico and Qatar
22 February 2017Mexico/Qatar: Fives has released information on cement plant projects in Mexico and Qatar. It commissioned a second FCB Horomill unit on 31 January 2017 at the cement grinding plant of Cementos Fortaleza, as part of the new 3300t/day complete line under construction at the Tula cement plant in Hidalgo. The first unit was commissioned in early December 2016.
Fives FCB was awarded the engineering, procurement and construction (EPC) contract from Cementos Fortaleza in mid-2015 for the design, supply, erection and commissioning of the cement production line. It includes a burning line using a FCB Kiln, FCB Zero-NOx Precalciner, FCB Preheater and Pillard Novaflam burner; raw meal and cement grinding plants using FCB Horomill and associated FCB TSV™ Classifiers; and a petcoke grinding plant using a FCB B-mill and associated FCB TSV Classifier. The FCB Horomill raw meal grinding plant and FCB Kiln are scheduled for commissioned in the second quarter of 2017.
In Qatar, Fives commissioned a cement milling unit on 6 February 2017 for Qatar National Cement Co.'s fifth production line in Umm Bab. This follows the commissioning of another mill at the site on 25 January 2017.
The mills are part of a 5000t/day production line that Fives is building for the client covering raw material preparation to cement despatch. The equipment ordered includes one 6400 kW FCB B‑mill with a FCB TSV7500 Classifier for the raw meal grinding plant, one five-stage FCB Preheater and a FCB Zero-NOx Precalciner, along with a FCB Kiln for the burning line, two TGT process filters and two 4200 KW FCB B‑mills with their FCB TSV4000 Classifiers for the cement grinding plant.
Qatar National Cement Company to build new cement line
01 April 2014Qatar: Qatar National Cement Company (QNCC) has signed a letter of intent with Fives FCB to build a fifth cement plant line with a clinker production capacity of 5000t/day. Fives FCB and TPF Basse Sambre will work together to finalise the contract documents by the end of April 2014.
The turkey contract has been valued at US$261m. Construction will start after handing over the site on a phased manner, starting with two cement mills which will be delivered after 17 months and 19 months. The overall project will be completed in 27 months.
Fives FCB was also the contractor for the construction of plant lines two, three and four. QNCC's production capacity is expected to rise to 17,000t/day of clinker and its grinding capacity will rise to 20,000t/day.
Lafarge Republic orders cement grinding plant from Fives
20 November 2013Philippines: Lafarge Republic signed a contract with Fives FCB for a new cement grinding plant for the Teresa plant located in Rizal province. The proposed plant will add 850,000t/yr production capacity to the Teresa plant's capacity in 2015. No financial information for the contract has been released.
The contract includes raw material feeding, with clinker and pulverised coal fed through the existing circuit and other additives, such as a limestone, gypsum, fly ash, fed by truck dump. A cement grinding workshop will be fitted with one Horomill® 3800 and one TSV™ 4500 classifier, associated with a dryer-aerodecantor and a TGT™ filter (under Fives Solios licence). A Fives Pillard vertical hot gas generator (12 MW) for the pouzzolana (25% moisture) drying will also be fitted.
The plant's cement silo will have a capacity of 5000t. A new cement transport system will connect the new silo, the site's existing silos and the packing plant. The contract also includes the control and supervision system and an electrical sub-station for the new build.