Medcem completes testing of WHR facility 07 April 2025
Türkiye: Medcem has completed testing of its new waste heat recovery (WHR) facility, which will recover 25% of the energy demand of the plant’s second rotary kiln line commissioned in 2024.
The 9.6MW facility uses an organic rankine cycle (ORC) system to generate electricity from a single heat source. The company says that this will lead to significant cost savings in energy expenses while also reducing CO₂ emissions.
Ghana faces cement shortage amid clinker crisis 07 April 2025
Ghana: Cement dealers have raised concerns over a growing shortage of brands including SOL Cement, Empire Cement and Dzata Cement, according to Citi Newsroom. Dealers have cited a scarcity of clinker and rising port charges behind recent supply disruptions and price increases. One cement retailer, Augustine Aduful, said that they paid for cement but have been left out of pocket for two weeks. Ghacem, in particular, has reportedly been facing a shortage, with customers having to switch to alternatives like Diamond Cement.
Ghana Chamber of Construction Industry CEO Emmanuel Cherry said that Ghana cannot continue to rely solely on clinker in cement production and that the country should begin to look for viable alternatives.
Another retailer, Isaac Frimpong, said “The clinker shortage is being caused by overseas supply issues. Even the recent price hikes are tied to external factors. We hope that with government intervention, the situation will stabilise.”
Trinidad to cut cement import duty to zero 07 April 2025
Trinidad & Tobago: The government will reduce the rate of duty on other hydraulic cement from 10% to 0%, following the fifth price rise by Trinidad Cement since 2021, including the most recent 7% increase in early 2025.
The nation’s cabinet suspended its cement quota and registration system in February 2024. Cement remains on the import negative list, requiring a licence and compliance with Caricom standards. The legal order for the duty cut will be published in the coming days.
Saudi Arabia: Sinoma Overseas has marked the construction of the preheater tower as part of a relocation and upgrade of Yamama Cement’s production line. The previously 10,000t/day line now has a capacity of 12,500t/day. The placement of the final structural element on the preheater tower was attended by representatives from both companies.
Sinoma posted on social media that the company had “overcom[e] significant engineering and logistical challenges – from dismantling and moving massive equipment to integrating new technology.”
With the preheater tower now complete, the company looks ahead to the plant’s commissioning and final delivery.
China: Hebei Wushan Cement has completely dismantled a 1000t/day clinker line formerly used to support its 3000t/day clinker line. The line will not resume production.
The producer also dismantled the original rotary kiln of a 2000t/day line and upgraded it to a 3000t/day new dry-process clinker line using a rotary kiln (Φ = 4.3m, L = 60m).