Mexico: France’s Fives has issued an update on the two raw meal grinding plants it is supplying to Cruz Azul’s Hidalgo and Oaxaca Lagunas cement plants.
Construction work at the Oaxaca Lagunas plant started in August 2018. Mechanical erection of the raw materials feeding workshop and the FCB Horomill grinding circuit started in July 2019. Electrical installation is currently under progress. The raw meal grinding workshop is scheduled to be operational by the end of March 2020.
Construction work at the Hidalgo plant started in December 2018. Mechanical erection started at the end of August 2019, electrical erection works will start in December 2019. First raw meal date is scheduled by the end of May 2020.
Both orders were finalised in November 2017. The Hidalgo plant ordered a 280t/hr grinding unit and the Oaxaca Lagunas plant has ordered a 300t/hr grinding unit. Each raw grinding plant features an FCB Horomill 4000mm grinding mill, a FCB TSV Classifier 6500 mm and a FCB Aerodecantor.