Australia: Adbri has reported that the ongoing upgrade at its Kwinana cement plant, previously estimated to cost US$137m, is now likely to cost closer to US$157m. It cited inflation and supply chain issues as the main reasons behind the 15% increase to the cost of the project, which seeks to combine its Western Australia operations at a single site, while raising its capacity by 36% to 1.5Mt/yr. The company said the upgrade was about 25% compete as at 30 June 2022, while procurement was about 75% committed. It is scheduled for commissioning in mid 2023.
Elsewhere, Adbri has also said that its definitive feasibility study for a Kalgoorlie lime kiln is on track for completion in the first half of 2023. The study includes mine planning and front-end engineering design.