The energy intensive cement industry faces high and rising energy costs and must meet requirements for reducing CO2 emissions. One remedy for these challenges is to increase energy efficiency by recovering waste heat and converting it to electricity.
Modern cement plants can be thought of as huge heat exchangers. After firing the kiln (and eventually the precalciner), the heat in the stack gas and from the hot clinker can be used to a large extent in the plant for:
- Secondary air preheating,
- Tertiary air preheating,
- Preheater tower with 3–6 stages to preheat raw meal,
- Preheater waste gas to dry raw meal in the raw mill,
- Waste heat recovery to dry and preheat conventional or alternative fuels,
- Use of clinker cooler waste heat to feed districtheating systems.
Waste heat recovery is the most important measure towards decreasing heat losses and therefore has the highest priority. It is the most efficient way to increase energy efficiency because the efficiency of heat recovery is high, 1kWh of waste heat reused in the plant ends in 1kWh of useful heat.