Aman Group inaugurates new mill 24 May 2017
Bangladesh: Aman Group has opened its second cement grinding plant at its Narayanganj complex, located 20km south of the Bangladeshi capital Dhaka. The new plant has a production capacity of 10,000t/day (~3.5Mt/yr), which, along with its first grinding plant, comfortably makes Aman the largest cement producer in the country. Commerce Minister Tofail Ahmed inaugurated the plant at the International Convention Centre Bashundhara in Dhaka on 23 May 2017.
Germany’s Loesche GmbH supplied the LM 56.3+3 CS type mill, which can grind Portland or composite cement to a fineness of 3200 Blaine. It can also grind granulated blast furnace slag at 175t/hr to a fineness of 4500 Blaine. In addition to the mill, the scope of supply also included additional technical equipment for the grinding plant such as a rotary feeder, 2-way chute, metal detector and permanent magnet drum separator.
Massive mill order for Loesche in Egypt 24 May 2017
Egypt: Germany’s Loesche GmbH has been contracted to supply 18 new vertical roller mills to China’s Sinoma CDI, which is building a six line cement plant at Beni Suef on behalf of the Egyptian Ministry of Defence. Each line will have a capacity of 6000t/day (12.6Mt/yr), making the plant one of the largest in the world.
Six raw mills, each with a capacity of 500t/hr, will grind cement raw material to a fineness of 12% R 90μm, six powerful cement mills, each with a throughput of 350t/hr will grind clinker to a fineness of 3200 Blaine and six Loesche coal mills will grind coal to a fineness of 10% R 90μm.
It is anticipated that the mills will be delivered within 2017, putting high demands on the delivery time of the mill components. Thanks to their long-standing experiences from a variety of fast-track-projects Loesche was able to carry conviction to the Ministry of Defence and assure the expected quick market entry with an elaborated plan of delivery.