Cemex and SUEZ mark alternative fuel milestone at Rugby cement plant
11 December 2024UK: Cemex and SUEZ Recycling and Recovery have celebrated the use of 1Mt of alternative fuel at Cemex’s Rugby cement plant since the adjacent SUEZ Malpass Farm facility opened in 2015. The partnership has reduced coal consumption at the plant by over 750,000t, alongside downstream CO₂ savings from supply chain emissions transporting and shipping coal on-site.
SUEZ processes non-recyclable materials at Cemex’s Rugby facility to produce Climafuel. The fuel is derived from sifted and shredded waste from local authorities and businesses in the Midlands, and is used to heat the kiln at the neighbouring Cemex plant. Ash from the Climafuel is also incorporated into clinker production.
Phil Baynes-Clarke, director of cement operations for Cemex UK, said “Since 2013, we have collaborated closely with SUEZ to produce Climafuel, a refuse-derived, non-fossil-based alternative fuel used to heat the kiln in the cement-making process. Over the past decade, Climafuel usage has steadily increased at our Rugby cement plant. Our ultimate goal is to operate the kiln with 100% alternative fuels, and we are getting close to this target.”
Commissioning to start at new UK SRF facility
12 February 2015UK: SITA UK has completed the construction of its Solid Recovered Fuel (SRF) manufacturing plant at Malpass Farm in Rugby, Warwickshire. The plant will undergo a series of commissioning tests over the next few months before starting full-scale production of Climafuel SRF. This will be used to power the kiln at the adjacent Cemex UK Rugby cement plant.
The residual waste material arriving at the site will primarily be collected from commercial and industrial businesses across the region that would otherwise go to landfill. Once received on site any metals, plastics and paper will be extracted for recycling. Similarly, materials with a high chlorine content, which could damage the kiln, will also be extracted. Any residual waste material that is removed from the production process will be processed into refuse derived fuel (RDF) for use in waste-to-energy applications.
To produce the SRF, the remaining material is sifted, shredded and blended while being continuously analysed using infrared technology. This allows the plant operators to ensure that the fuel, which has a confetti-like consistency after processing, has the precise chemical composition and calorific value required by Cemex UK.
SITA UK's Head of Alternative Fuels, Andy Hill, said, "The residual waste material that will be delivered to this facility would have gone to landfill but, instead, we are going to take out anything that can be recycled and then turn what's left into a replacement fuel."
"We have been producing this fuel very successfully at our sister plant at Landor Street in Birmingham for the past couple of years, but this new facility implements the latest technology and will substantially increase our production capacity," continued Hill. "Between the two plants, we'll be producing around 250,000t/yr of Climafuel."
SITA UK is currently also investing in new SRF manufacturing facilities at the Port of Tilbury in Essex, which are currently under construction. SITA UK currently supplies SRF to CEMEX UK and to CEMEX Latvia.