04 April 2025
Saudi Arabia: Sinoma Overseas has marked the construction of the preheater tower as part of a relocation and upgrade of Yamama Cement’s production line. The previously 10,000t/day line now has a capacity of 12,500t/day. The placement of the final structural element on the preheater tower was attended by representatives from both companies.
Sinoma posted on social media that the company had “overcom[e] significant engineering and logistical challenges – from dismantling and moving massive equipment to integrating new technology.”
With the preheater tower now complete, the company looks ahead to the plant’s commissioning and final delivery.
China: Hebei Wushan Cement has completely dismantled a 1000t/day clinker line formerly used to support its 3000t/day clinker line. The line will not resume production.
The producer also dismantled the original rotary kiln of a 2000t/day line and upgraded it to a 3000t/day new dry-process clinker line using a rotary kiln (Φ = 4.3m, L = 60m).
Kavkazcement to modernise amid rising costs 04 April 2025
Russia: Kavkazcement plans to spend US$224m on equipment modernisation after cement production costs rose by 30–34% in 2024, according to local news reports. The producer recorded a production increase of 11% year-on-year to 2Mt in 2024 and aims to grow output by a further 10% in 2025.
General director Sergey Bogomaz said “Cement from Kavkazcement is in demand in many regions of Russia. The main deliveries go to the Rostov Region, Volgograd Region and Krasnodar Krai. In our region, we see an increase in construction volumes. New infrastructure projects are emerging, such as the construction of the first airport in Karachay-Cherkessia.”
Cherat Cement commissions Khyber Pakhtunkhwa solar plant 04 April 2025
Pakistan: Cherat Cement has commissioned a 6MW solar power plant at its facility in Khyber Pakhtunkhwa. The project forms part of a 9MW total capacity, with the remaining 3MW expected to be commissioned in the 2025 financial year. The company did not disclose its total renewable energy capacity in the notice.
Thatta Cement commissions wind project 04 April 2025
Pakistan: Thatta Cement commissioned its 4.8MW wind power project at its plant in Thatta, Sindh, on 3 April 2025. The project was reportedly completed ahead of schedule and brings the producer’s total renewable energy capacity to 9.8MW.