Kuwait Cement hires Magotteaux for mill upgrades 29 March 2019
Kuwait: Kuwait Cement has hired Belgium’s Magotteaux to modernise three of its cement mills. The project consists of closing the open circuit with fourth generation XP4i separators, installing new mill internals components, including diaphragms, and adapting a new ball charge gradation. The aim of the project is to increase the production rate, reduce the specific energy consumption and improve the product quality, by reducing the residue on 45μm by keeping the same Blaine value.
Qizilqumsement starts US$110m upgrade 28 March 2019
Uzbekistan: Qizilqumsement has started building a US$110m upgrade to its Qizilqum cement plant. The project is intended to increasing the plant’s clinker production capacity and decrease energy costs. It is scheduled for completion in 2020.
Almalyk starts exporting cement to Afghanistan 28 March 2019
Afghanistan/Uzbekistan: Uzbekistan’s Almalyk Mining and Metallurgical Complex (AMMC) has started exporting cement to Afghanistan. A trial consignment of Ordinary Portland Cement (OPC) was despatched from the company’s new 1.5Mt/yr Sherabad cement plant in Surkhandarya, according to the Trend News Agency. It intends to export 0.5Mt/yr to Afghanistan. As part of a contract signed with the Hamid Company just under 1000t of cement has been sent by train to Mazar-i-Sharif.
France: LafargeHolcim France has started the second phase of a Euro100m upgrade project its Martres-Tolosane cement plant. It is starting the construction phase of a new production line following the completion of site preparation and civil engineering. French company Boccard is coordinating the work. Commissioning of the upgrade is scheduled for mid-2020.
Eurocement upgrading Katavsky and Kavkaztsement plants 28 March 2019
Russia: Eurocement is close to completing a Euro2.5m upgrade to a cement grinding mill at its Katavsky cement plant. The project was intended to improve the quality of its cement products and to replace the mill’s filter sleeves. The unit uses which Christian Pfeiffer separators, Aumund elevators, Siemens automation systems and mill grinders and Vega grinding media. Pre-commissioning is currently being completed and cement from the mill is being tested at a laboratory.
The cement producer’s Kavkaztsement plant is building a captive power plant scheduled for commissioning in August 2019. It has completed the construction of the building that will house the gas piston power station as well as other connecting structures. Employees from the plant are being trained by Wärtsilä in preparation for the start up. The project has an investment of around Euro15m.